Mandatory campus network upgrades occurring Monday, January 6, 2014, through Saturday, January 18, 2014 will require network outages. Services such as email, file shares, internet access, and network printing on desktop computers and wireless devices will not be available for short periods on a building by building basis.  As work is performed at each building location, signs will be posted indicating "Network Upgrade in Progress."
  
Figure 1: sample poster to be posted on buildings as work is performed

Please note, if upgrades proceed faster than planned, ITS will advance to the next location upgrades on the list – possibly the following day's upgrades.

The following facilities will not be affected:

  • The Student Health Center
  • Foundation
  • University Student Union
  • Student Housing Offices, Dormitories and Dining Facilities
  • Bookstore
  • Barrett Athletic Administration Center
  • Parking & Transportation Services
  • Recycling Center
  • Soroptimist House
  • Student Recreation and Wellness Center

Status Updates

Starting January 6, 2014, this list will provide regular progress updates, so please check back regularly. This list is in sequential order that the work is planned to be performed. An alphabetical list is also available if you prefer.

Building

Floor/Area

Status

Faculty Office 2

all

Completed 12/16/13

Brotman Hall

ITS area

Completed 1/6/14

Brotman Hall

1st floor, Enrollment Svcs

Completed 1/6/14

Nursing

Old Nursing building

Completed 1/6/14

Nursing

New Nursing building

Completed 1/6/14

Visitor Information Center

all

Completed 1/6/14

Family Consumer Sciences

all

Completed 1/6/14

College of Business Administration

1st floor

Completed 1/6/14

College of Business Administration

Wireless for rotunda

Completed 1/6/14

Psychology

Lower level and Rms 100-120

Completed 1/6/14

Psychology

1st floor Rms 121+ and all of 2nd floor

Completed 1/6/14

Psychology

3rd and 4th floors

Completed 1/6/14

Liberal Arts 5

1st floor

Completed 1/6/14

Liberal Arts 1

1st floor

Completed 1/7/14

Liberal Arts 1

2nd and 3rd floors

Completed 1/7/14

Faculty Office 3

Lower level

Completed 1/7/14

Faculty Office 3

1st and 2nd floors

Completed 1/7/14

Faculty Office 3

3rd floor

Completed 1/7/14

Lecture Halls 150/151

all

Completed 1/7/14

Library and Academic Services

Library lower level north side

Completed 1/7/14

Library and Academic Services

Library 2nd floor

Completed 1/7/14

Library and Academic Services

Library 2nd floor, south offices

Completed 1/7/14

Library and Academic Services

AS 3rd floor

Completed 1/7/14

Library and Academic Services

Library 5th floor north

Completed 1/7/14

Library and Academic Services

Library 5th floor south

Completed 1/7/14

Library and Academic Services

Library 3rd floor

Completed 1/7/14

KKJZ

all plus LA2

Completed 1/8/14

Library and Academic Services

Library Lower level and 1st floor south side

Completed 1/8/14

Library and Academic Services

Library 1st floor remainder

Completed 1/8/14

Library and Academic Services

AS 2nd floor

Completed 1/8/14

Liberal Arts 2

Wireless for Rm 109

Completed 1/8/14

Multimedia Center

all

Completed 1/8/14

Education 1

North offices and classrooms

Completed 1/8/14

Education 1

South offices

Completed 1/8/14

Education 2

all

Completed 1/8/14

MacIntosh Humanities Building

Floors 6-9

Completed 1/8/14

MacIntosh Humanities Building

Floors 1-5

Completed 1/8/14

Language Arts Building

1st floor

Completed 1/8/14

Language Arts Building

2nd floor

Completed 1/8/14

Language Arts Building

3rd floor

Completed 1/8/14

Studio Theater

1st floor

Completed 1/8/14

Studio Theater

2nd floor

Completed 1/8/14

University Telecommunications Center

1st floor

Completed 1/8/14

University Telecommunications Center

2nd floor

Completed 1/8/14

Library and Academic Services

AS 1st floor

Completed 1/9/14

University Theater

all

Completed 1/9/14

Fine Arts 1

all

Completed 1/9/14

Fine Arts 2

west side

Completed 1/9/14

Fine Arts 2

east side

Completed 1/9/14

Fine Arts 3

all

Completed 1/9/14

Fine Arts 4

all

Completed 1/9/14

Faculty Office 4

all

Completed 1/9/14

Peterson Hall 1

1st and 2nd floor mixture

Completed 1/9/14

Peterson Hall 1

2nd floor remainders

Completed 1/9/14

Peterson Hall 2

lower level

Completed 1/9/14

Peterson Hall 2

1st floor

Completed 1/9/14

Peterson Hall 2

2nd floor

Completed 1/9/14

Microbiology

lower level

Completed 1/10/14

Microbiology

100 level

Completed 1/10/14

Microbiology

200 level

Completed 1/10/14

Microbiology

300 level

Completed 1/10/14

Faculty Office 5

all

Completed 1/10/14

Hall of Science

Lower level

Completed 1/10/14

Hall of Science

1st floor

Completed 1/10/14

Hall of Science

2nd floor

Completed 1/10/14

Molecular Life Sciences Center

1st floor west

Completed 1/10/14

Molecular Life Sciences Center

1st floor east

Completed 1/10/14

Molecular Life Sciences Center

controls system east side

Completed 1/10/14

Molecular Life Sciences Center

2nd floor west

Completed 1/10/14

Molecular Life Sciences Center

2nd floor east

Completed 1/10/14

Molecular Life Sciences Center

3rd floor west

Completed 1/10/14

Molecular Life Sciences Center

3rd floor east

Completed 1/10/14

Horn Center

Open Lab area

Completed 1/11/14

College of Business Administration

2nd and 3rd floor, Labs

Completed 1/11/14

Liberal Arts 5

2nd and 3rd floors

Completed 1/11/14

Library and Academic Services

Library 4th floor

Completed 1/11/14

Corporation Yard

South wing, Planning to Mail room

Completed 1/11/14

Hall of Science

3rd floor

Completed 1/14/14

Central Plant

all

Completed 1/14/14

Health and Human Services 2

all

Completed 1/14/14

Horn Center

northeast

Completed 1/14/14

Horn Center

southwest

Completed 1/14/14

Horn Center

Art Museum

Completed 1/14/14

Social Sciences/Public Affairs

lower level

Completed 1/14/14

Social Sciences/Public Affairs

1st floor

Completed 1/14/14

Social Sciences/Public Affairs

2nd and 3rd floors

Completed 1/14/14

Kinesiology

east side

Completed 1/14/14

Kinesiology

center

Completed 1/14/14

Kinesiology

west side

Completed 1/14/14

Health and Human Services 1

all

Completed 1/14/14

Vivian Engineering Center

1st and 2nd floors

Completed 1/14/14

Vivian Engineering Center

4th floor

Completed 1/14/14

Engineering 2

all

Completed 1/14/14

Engineering 3

all

Completed 1/14/14

Engineering 4

all

Completed 1/14/14

Design

north side

Completed 1/14/14

Human Services & Design

all

Completed 1/14/14

Vivian Engineering Center

3rd floor

Completed 1/15/14

Vivian Engineering Center

5th floor

Completed 1/15/14

Design

south side

Completed 1/15/14

Engineering Technology

east side

Completed 1/15/14

Engineering Technology

west side

Completed 1/15/14

University Music Center

C section

Completed 1/15/14

University Music Center

A section, east

Completed 1/15/14

University Music Center

C section, far east

Completed 1/15/14

Carpenter's Performing Art Ctr/Dance

west side, Dance

Completed 1/15/14

University Music Center

A section, west

Completed 1/15/14

Carpenter's Performing Art Ctr/Dance

Stage area

Completed 1/15/14

Carpenter's Performing Art Ctr/Dance

Dance offices, F section

Completed 1/15/14

Carpenter's Performing Art Ctr/Dance

Dance center and offices

Completed 1/15/14

Engineering Computer Science

1st floor

Completed 1/15/14

Engineering Computer Science

2nd and 3rd floors

Completed 1/15/14

Engineering Computer Science

5th and 6th floors

Completed 1/15/14

Carpenter's Performing Art Ctr/Dance

east side offices

Completed 1/15/14

Engineering Computer Science

4th floor classrooms and printers

Completed 1/16/14

College of Business Administration

2nd floor east of elevator

Completed 1/16/14

University Police

all

Completed 1/16/14

Facilities Management/Safety & Risk Mgmt

all

Completed 1/16/14

Corporation Yard

warehouse

Completed 1/16/14

Corporation Yard

north shops

Completed 1/16/14

Isabel Patterson Child Development Ctr

rotunda and office

Completed 1/16/14

Isabel Patterson Child Development Ctr

laundry

Completed 1/16/14

Isabel Patterson Child Development Ctr

addition to west

Completed 1/16/14

University Print Shop

all

Completed 1/16/14

Pyramid

Ukleja, Volleyball, and court

Completed 1/16/14

Pyramid

Basketball, Events, old Frog's

Completed 1/16/14

Brotman Hall

Bursar's Office, Fin.Mgmt., ES across from ITS

Scheduled for 1/18/14

Brotman Hall

2nd and 3rd floor, northwest

Scheduled for 1/18/14

Brotman Hall

2nd and 3rd floor, southeast

Scheduled for 1/18/14

University Dining

all UDP down on same day

Scheduled for 1/18/14

University Dining

all UDP down on same day

Scheduled for 1/18/14

University Dining

all UDP down on same day

Scheduled for 1/18/14

University Dining

all UDP down on same day

Scheduled for 1/18/14